A kitchen renovation usually takes 6 to 12 weeks for the construction work, but the complete process from planning to final completion can take around 3 to 6 months depending on the kitchen size, design changes, material availability, and the type of renovation.
Step-by-Step Procedure
Planning & Material Ordering (Weeks 1–6, Before Demo)
Finalize layout drawings and choose all appliances, tiles, and fixtures.
Order cabinets (4 to 10 weeks delivery window) and secure city building permits (1 to 3 weeks).
Demolition & Rough-In (Weeks 1–3 of Construction)
Remove old cabinets, flooring, and appliances (2 to 5 days).
Update plumbing pipes, electrical wiring, and air vents inside open walls (1 to 2 weeks).
Walls, Flooring & Cabinets (Weeks 4–6 of Construction)
Hang new drywall, paint base coats, and lay down flooring (1 to 2 weeks).
Set and level the base and upper cabinets (3 to 5 days).
Countertops & Backsplash (Weeks 7–9 of Construction)
Fabricators measure (template) the installed cabinets; cutting stone takes 1 to 2 weeks.
Install stone slabs (1 day) and tile the wall backsplash (2 to 4 days).
Hookups & Final Details (Weeks 10–12 of Construction)
Connect sink, faucet, dishwasher, stove, and light fixtures (2 to 4 days).
Install cabinet handles, complete paint touch-ups, and pass final city inspection (1 week).
6. Worktops, Appliances, and Finishing: 1–2 Weeks
Worktops are installed, appliances are connected, splashbacks are completed, and final adjustments are made.
Factors That Affect Renovation Time
- Kitchen size: Larger kitchens require more installation time.
- Custom cabinetry: Bespoke kitchens can add several weeks due to manufacturing and fitting.
- Structural changes: Removing walls or changing layouts may add 4–8 weeks.
- Material availability: Delays in cabinets, worktops, or appliances can extend the project.
- Contractor scheduling: Multiple trades must be coordinated to avoid downtime.
A kitchen renovation usually takes 6 to 12 weeks to complete, depending on the size of the kitchen, the level of structural work required, and the availability of materials and tradespeople. A simple kitchen update may take 2–4 weeks, while a full renovation involving plumbing, electrical work, flooring, or layout changes can take 3–6 months.